Capital Project 2024 Renderings
Capital Project Update March 20, 2023 Design Renderings FOR INFORMATIONAL PURPOSES ONLY – View the Design Renderings
Renderings may not reflect the final design and are intended as an option for consideration.
-
Phase 1 New Transportation Building
Approximate construction timeline Jan 2023 - August 2024- Inground lifts
- Wash system
- Fuel island
-
Phase 2 Middle/High School Renovations
Approximate construction timeline January 2024 - August 2025- New main entry
- Classroom upgrades
- Locker room renovations
- Restroom upgrades
- Parking lot renovations
Phase 2 Elementary School Renovations
Approximate construction timeline December 2024 - September 2025- Classroom upgrades
- Restroom upgrades
Phase 2 Athletic Complex
Approximate construction timeline January 2024 - December 2024- Multipurpose turf field
- Bleachers
- Lighting and sound system