Capital Project 2024 Phase 3

Phase III - Courtyard and District Office
December 2025
The General Trades Contractor completed the metal stud framing and began installing the insulation and hanging the gypsum wall board. The Electrical Contractor completed the in-wall electrical rough, and The Mechanical Contractor started roughing in the new ductwork and piping. Outside in the corridor, the General Trades Contractor removed a section of lockers and completed the wall infill.
November 2025
The General Trades Contractor has completed most of the metal stud framing at both the interior and exterior portions of the building. The in wall electrical rough is ongoing and will continue into mid-December. The Mechanical Contractor is expected to receive most of their equipment the week before the Holiday recess and will work over the holiday recess to install much of their associated piping. The General Trades Contractor will receive a shipment of gypsum wall board and insulation the first week of December and will commence with the installation towards the end of December.
October 2025
The General Trades Contractor has completed selective demolition within both the District Office and Business Office. The mechanical, electrical, and plumbing trades have been working alongside the General Trades Contractor performing disconnects and removals. The General Trades Contractor has started installing metal stud framing within the new spaces and will continue with studs and board in November. Outside, the General Trades Contractor has completed the removal of the sidewalk section and started installing the new building foundations.
August 2025
The Phase III Sitework contractor completed all work within the courtyard and turned it over to the Turf Contractor for installation of the new turf. All work within the courtyard was completed by the middle of August.
July 2025
The Phase III Site Contractor continued work within the main High School Courtyard; new drainage has been installed, the subgrade was prepped, and a portion of the new concrete sidewalk was poured.
Additional settings for Safari Browser.
