Capital Project 2024 Phase 3

 

 

Image promoting the Livonia Central School District's Capital Project 2024.

 

Phase III - Courtyard and District Office

 

 

 

 

May 2026

The General Trades Contractor began installing wall tile in the new vestibule area. There were some deficiencies noted with the installation that were discussed during a field walkthrough. The General Trades Contractor is taking corrective action and will work to ensure a better quality finished moving forward in the corridors. Additionally, the General Trades Contractor applied moisture mitigation and prepped the concrete to receive new flooring. The Mechanical Contractor completed the installation of the new roof top unit, and the unit was started up. The Electrical Contractor ordered new thinner light fixtures in lieu of reusing existing due to ceiling elevation issues with new ductwork.  
 
Outside, the concrete walkway to the new vestibule was prepped and poured. Some additional concrete was removed near the flagpole to accommodate an slight elevation change. Due to all the concrete directly adjacent to the flagpole remaining, the new flagpole light is going to be mounted on a concrete pedestal in the lawn area in lieu of being mounted to the pole. 

A modern office space with blue walls and patterned carpet.

Flooring Install

An empty room with patterned carpet and large windows showing greenery outside.

Flooring Install

An empty room with new patterned carpet tiles being installed.

Flooring Install

A bright hallway with large windows overlooking a brick building and green grass.

New Courtyard Storefront

Exterior view of a modern building entrance with large windows and a brick facade.

New Courtyard Storefront

An unfinished hallway with exposed ceiling elements and bare walls.

Vestibule Tile Installation

A long, single-story building with many windows, possibly a school or office, under a cloudy sky.

Sidewalk Prep

An outdoor paved walkway leads past a building with orange siding and a fence.

Vestibule Sidewalk

April 2026

The General Trades Contractor made all the layout modifications noted in the change order issued last month. This included the installation of a new steel column at the vestibule. The General Trades Contractor also continued priming and painting walls and installed new exterior windows throughout both spaces. Additionally, The General Trades Contractor began installing acoustical ceiling grid and dropping border tiles. The Plumbing Contractor made final connections to the existing building plumbing to accommodate the new sink in the District Office Break Room. The Mechanical Contractor delivered the new roof top unit, set the unit in place, and began making final connections. The old units were removed and the curbs were capped. The Electrical Contractor completed the wiring at the new roof top unit and began installing devices 
such as power receptacles and switches.

New Steel Column Install

New Steel Column Install

New Exterior Windows & Radiant Fintube

New Exterior Windows and Radiant Fintube

New Exterior Windows and Radiant Fintube

New Exterior Windows and Radiant Fintube

Reception Doorway Layout Modification

Reception Doorway Layout Modification

Transaction Window Layout Modification and Partial Infill

Transaction Window Layout Modification and Partial Infill

New Steel Column Install

New Steel Column Install

Courtyard Storefront Removal & New Framing

Courtyard Storefront Removal & New Framing

March 2026

The General Trades Contractor began priming and painting walls where possible. The new drop box in the treasurer’s office was installed, and the new exterior metal panels were measured up and put into production. The Plumbing Contractor installed domestic water and drainage pipe for the new sink in the district office break room. The Electrical Contractor installed the new power outlet within the floor of the conference room and pulled wire through previously installed conduit for the new roof top unit. The roof top unit is expected to arrive April 6th.

Regarding modifications to the project, a change order has been processed to infill a portion of the transaction window at the vestibule, swap a framed doorway into a cased opening, remove an existing steel column and relocate with a new smaller steel column. That change order was approved Monday March 30th, the General Trades Contractor has scheduled the remaining carpentry work to recommence towards the middle of next week. The tile installation has been scheduled to start the week of April 13th.

A room under renovation with a bright blue accent wall and painting supplies.

District Office

An interior room under construction with a bright blue wall and unfinished concrete floor.

Business Office

An interior room under construction with a bright blue wall, exposed ceiling wires, and a red ladder.

Business Office

An unfinished room with white and blue walls, concrete floor, and exposed ceiling pipes.

Assistant Superintendent’s Office

A red ladder stands in an unfinished room with one wall painted a deep blue.

Business Office

February 2026

The General Trades Contractor completed the installation of the gypsum wall board including all finishing work such as mudding, taping, and sanding. The Plumbing Contractor completed the in-wall plumbing rough for the new corridor drinking fountain located outside the new business suite. The Electrical Contractor relocated an existing electrical panel from within the old computer lab to the new electrical closet directly outside the new business suite. Additionally, the Electrical Contractor pulled new wiring through previously roughed conduit and is waiting for the walls to receive primer and their 1st coat of paint before installing devices.

Outside, the General Trades Contractor installed rigid insulation and exterior grade sheathing with a pre-applied vapor barrier at the courtyard infill. Additionally, the roof was tied into the new wall system per the details provided by the Architect.

Regarding modifications to the project, a change order has been processed to add wall tile to the new wall sections within corridor 002 which is the corridor that adjoins the District Office and Business Suite. That tile order has been released, and the General Trades Contractor is working to get that tile onsite. A few other recent modifications were received in regards to infilling a portion of the transaction window at the vestibule, swapping a framed doorway into a cased opening, removing an existing steel column and relocating with a new smaller steel column, and shifting the interior set of vestibule doors. That change has been received by the applicable contractors and is being priced up 
for review. Priming and painting of the rooms not affected by the change will start in March.

An interior view of a room with wooden paneling and a window.

District Office Vestibule

An excavator stands ready on a construction site under a cloudy sky.

Stormwater Separator for Parking Lot Reconstruction

A long hallway under construction with exposed ceiling elements.

District Office Main Corridor

An unfinished room with exposed ceiling beams and partially installed wall panels.

District Office Breakroom

Exterior view of a modern building with large windows and a covered entrance.

Sheathing Installed at Entrance Vestibule

A gray electrical panel is mounted on a blue wall.

Panel Relocation to New Electrical Closet

Exterior view of a building with a purple wall and boarded-up section.

Insulation Installed at Entrance Vestibule

January 2026

The General Trades Contractor began installing the insulation and gypsum wall board. They are tracking about 80% complete with the remaining 20% to be completed within the first two weeks of February. The plumbing Contractor completed the in-wall plumbing rough within the Business Suite for the new Kitchenette and began installing new pipe for the Corridor drinking fountain. The Mechanical Contractor completed all above ceiling and in-wall rough and is awaiting the completion of the walls and ceiling to start installing grills and diffusers. 

Storefront at Courtyard Vestibule Removed

Storefront at Courtyard Vestibule Removed

In-Wall Plumbing Rough

In-Wall Plumbing Rough

Corridor within District Office Suite

Corridor within District Office Suite

Opening for Transaction Window at District Office

Opening for Transaction Window at District Office

Cabinet Heater Within Vestibule Installed

Cabinet Heater Within Vestibule Installed

Math Hall Corridor

Math Hall Corridor

December 2025

The General Trades Contractor completed the metal stud framing and began installing the insulation and hanging the gypsum wall board. The Electrical Contractor completed the in-wall electrical rough, and The Mechanical Contractor started roughing in the new ductwork and piping. Outside in the corridor, the General Trades Contractor removed a section of lockers and completed the wall infill.

Interior view of a space under construction, with exposed framing and purple walls.

Transaction Window in Reception

A hallway with plywood flooring and blue tape marking sections.

Corridor Outside DO/Business Suite

A long hallway with blue and gray walls and several doorways.

Corridor Outside DO/Business Suite

An interior view of a room with open doorways and natural light.
Interior construction site with drywall and exposed ductwork.

Gypsum Board Installation

November 2025

The General Trades Contractor has completed most of the metal stud framing at both the interior and exterior portions of the building. The in wall electrical rough is ongoing and will continue into mid-December. The Mechanical Contractor is expected to receive most of their equipment the week before the Holiday recess and will work over the holiday recess to install much of their associated piping. The General Trades Contractor will receive a shipment of gypsum wall board and insulation the first week of December and will commence with the installation towards the end of December.

A newly poured concrete floor inside a partially constructed building.

District Office Slab Infill

Interior view of a building under construction, showing exposed framing.

District Office Framing

October 2025

The General Trades Contractor has completed selective demolition within both the District Office and Business Office. The mechanical, electrical, and plumbing trades have been working alongside the General Trades Contractor performing disconnects and removals. The General Trades Contractor has started installing metal stud framing within the new spaces and will continue with studs and board in November. Outside, the General Trades Contractor has completed the removal of the sidewalk section and started installing the new building foundations.

District Office Vestibule Construction

District Office Vestibule Construction

District Office Demolition

District Office Demolition

District Office Demolition

District Office Demolition

August 2025

The Phase III Sitework contractor completed all work within the courtyard and turned it over to the Turf Contractor for installation of the new turf. All work within the courtyard was completed by the middle of August. 

 
MHS Courtyard Turf Installation

MHS Courtyard Turf Installation

MHS Courtyard Turf Installation

MHS Courtyard Turf Installation

July 2025

The Phase III Site Contractor continued work within the main High School Courtyard; new drainage has been installed, the subgrade was prepped, and a portion of the new concrete sidewalk was poured.

 
MHS Courtyard

MHS Courtyard

MHS courtyard sidewalk

MHS courtyard sidewalk