Capital Project 2024 Phase 3

 

 

Image promoting the Livonia Central School District's Capital Project 2024.

 

 

 

 

 

 

 

Phase III - Courtyard and District Office

 

 

 

 

 

 

 

 

 

 

December 2025

The General Trades Contractor completed the metal stud framing and began installing the insulation and hanging the gypsum wall board. The Electrical Contractor completed the in-wall electrical rough, and The Mechanical Contractor started roughing in the new ductwork and piping. Outside in the corridor, the General Trades Contractor removed a section of lockers and completed the wall infill.

Interior view of a space under construction, with exposed framing and purple walls.

Transaction Window in Reception

A hallway with plywood flooring and blue tape marking sections.

Corridor Outside DO/Business Suite

A long hallway with blue and gray walls and several doorways.

Corridor Outside DO/Business Suite

An interior view of a room with open doorways and natural light.
Interior construction site with drywall and exposed ductwork.

Gypsum Board Installation

November 2025

The General Trades Contractor has completed most of the metal stud framing at both the interior and exterior portions of the building. The in wall electrical rough is ongoing and will continue into mid-December. The Mechanical Contractor is expected to receive most of their equipment the week before the Holiday recess and will work over the holiday recess to install much of their associated piping. The General Trades Contractor will receive a shipment of gypsum wall board and insulation the first week of December and will commence with the installation towards the end of December.

A newly poured concrete floor inside a partially constructed building.

District Office Slab Infill

Interior view of a building under construction, showing exposed framing.

District Office Framing

October 2025

The General Trades Contractor has completed selective demolition within both the District Office and Business Office. The mechanical, electrical, and plumbing trades have been working alongside the General Trades Contractor performing disconnects and removals. The General Trades Contractor has started installing metal stud framing within the new spaces and will continue with studs and board in November. Outside, the General Trades Contractor has completed the removal of the sidewalk section and started installing the new building foundations.

District Office Vestibule Construction

District Office Vestibule Construction

District Office Demolition

District Office Demolition

District Office Demolition

District Office Demolition

August 2025

The Phase III Sitework contractor completed all work within the courtyard and turned it over to the Turf Contractor for installation of the new turf. All work within the courtyard was completed by the middle of August. 

 
MHS Courtyard Turf Installation

MHS Courtyard Turf Installation

MHS Courtyard Turf Installation

MHS Courtyard Turf Installation

July 2025

The Phase III Site Contractor continued work within the main High School Courtyard; new drainage has been installed, the subgrade was prepped, and a portion of the new concrete sidewalk was poured.

 
MHS Courtyard

MHS Courtyard

MHS courtyard sidewalk

MHS courtyard sidewalk